Dear
Sir/Madam,
This
submission is being made by nearby residents of the proposed LNG regasification
terminal and by people with close family and economic ties to the area. We are
totally opposed to the planning application in its present form and ask that An
Bord Pleanála refuse planning permission to Shannon LNG.
It
must be highlighted that there are serious environmental, safety, economic,
residential-amenity and other concerns surrounding the proposed LNG terminal in
Tarbert parish, which have not been raised at all to date. These concerns may
be overlooked by the general public until it is too late as the decision by An
Bord Pleanála on whether or not to grant planning permission will already have
been made. This is because the new fast-track planning process allowed for this
application means that all environmental, safety and development issues are
being examined in parallel and by different government bodies without the right
of appeal in the planning process that would exist if the application was first
submitted to Kerry County Council. This is unacceptable because it is depriving
the public of meaningful or effective participation in the planning process due to information not being disclosed in
a timely manner and therefore removing the transparency that must continue to
exist in the planning process. This is contrary to both the Planning and
Development Act 2000 and the EU EIA directive. For this reason we herby insist
on being allowed to make more submissions once this information has been
obtained.
The
primary concern is the lack of safety for nearby residents due to the fact that
they live too close to the proposed site. Conservative scientific evidence
provided below shows that it is unsafe to live within 3 miles of the site. This
area covers the villages of Ballylongford, Tarbert and Killimer in County
Clare. More seriously, the limited QRA
undertaken by Shannon LNG itself admits categorically that a vapour cloud from
a leaked tank could travel as far away as 12.4
kilometers before being ignited (page 32). This will mean that the
Kerry towns and districts of Asdee, Moyvane and Beal, the Limerick town of Glin
and the Clare towns of Kilrush, Moyasta, Killimer, Knock and Kilmurry McMahon,
as well as surrounding countryside, are in the possible fallout zone. This is
from Shannon LNG’s own research.
This
will therefore also prevent further use being made of the rest of the land bank
due to the danger posed to people working nearby, if safety standards are in
fact implemented.
The
most serious environmental concern is that up to 100 million gallons of
chlorinated seawater will be pumped into the estuary daily, causing serious
environmental damage to the eco-system of this SAC area. The withdrawal and
discharge of huge volumes of seawater would affect marine life by killing
ichthyoplankton and other micro-organisms forming the base of the marine food
chain unable to escape from the intake area. Furthermore, the discharge of
cooled and chemically-treated seawater would also affect marine life and water
quality.
The
most serious economic concern is that the gas-industry’s own
standard-recommended exclusion zone of 2 miles around an LNG tanker will stop
shipping – including the Tarbert-Killimer car ferry - in the estuary every time
an LNG tanker is in the area (and Shannon LNG plan up to 125 tankers a year)
and prevent marine use of the rest of the land bank – if those safety standards
are implemented.
Finally,
whereas the developer emphasises that it is in the national strategic interest
to have an LNG terminal in Ireland, we are of the opinion that only a strategic
interest in LNG as another strategic alternative source of gas in Ireland has
been accepted and that there has been no acceptance of the strategic need for
an LNG terminal if no suitable site in Ireland is found. This distinction is
very important because this need for LNG is already being met with the
construction of the LNG terminals in the UK which can then provide LNG to Ireland
via the existing gas pipeline from the UK. It must also be noted that the
developer, in any case, does not guarantee supply of LNG via Tarbert. What is proposed is
no more than a private storage and transhipment facility albeit on a very large
scale. It does not purport to offer any strategic benefit to the country, nor
in reality does the country gain any strategic benefit from it. On the
contrary, it undermines the stated government policy. It does so in a number of
respects - in particular by entirely
prejudging the outcome of the all-Island study and the strategic goal No. 2 in
the government’s white paper on delivering a sustainable energy solution for
Ireland.(See 17 below). On that basis alone the application is clearly
premature and should be refused.
The
methodology used in this submission is to support each topic with data from
published scientific reports, governmental reports, decisions and strategy
documents, statutory regulations (both Irish and European) and from standards
produced by the Gas industry itself. Any reference to non-scientific based
claims will be clearly stated. Data was collected initially by various members
of the association individually. This was then followed on by a visit to the
Dragon LNG plant at Milford Haven in Wales on October 13th 2007
where the views of concerned residents were noted. Information was raised since
then in contacts with Shannon LNG at their office in Listowel on October 15th,
with other local residents in Tarbert in meetings with Shannon LNG representatives
on October 18th and October 29th, and with various governmental,
scientific, academic and voluntary organisations in Ireland and abroad. Our
concerns were taken seriously by one and all but many questions were left
unanswered. The overwhelming feedback has been that a submission of these
concerns needs to be made to An Bord Pleanála,
For the reasons given below we
submit that the Bord is obliged to refuse the application. We accept that the
Bord may of course take a different view. While we reserve our rights to
challenge such a view if necessary we make any comments on conditions that
could be applied by the bord if it grants permission to the developer entirely
without prejudice to our over-riding contention that this application should be
refused.
STATUTORY
REGULATIONS:
· Planning and Development
Acts 2000 – 2006. This includes the Planning and Development (Strategic
Infrastructure) Act 2006
· EU Habitats Directive
92/43/EEC On the conservation of
natural habitats and of wild fauna and flora– as 25 acres of the site is in a
Special Area of Conservation (SAC)
· EU 1998 Aarhus
Convention Directives, Directive 2003/4/EC and Directive 2003/35/EC – on the
right of the public to be informed on the environmental impact and being
provided with the opportunity to make comments and have access to justice
· EIA directive 87/337/EEC
as amended by Directive 97/11/EC -
concerning the effects of certain public and private projects on the
environment, the precautionary, preventative-action and polluter-pays principles
· Seveso II Directive
96/82/EC as amended by 2003/105/EC –
for placements of hazardous sites
· EU Water Framework
directive 2000/60/EC
· Kyoto Protocol
· County Clare and County
Kerry Development Plans
· European Convention on Human Rights Act 2003
· Planning and Development (Strategic Environmental Assessment)
Regulations 2004
INVALID APPLICATION
- The developers in
their planning application describe the 10 hectares to be developed
offshore as zoned industrial. This is false as it is zoned Special Area of
Conservation. We therefore object to this invalid and misleading
application and want the whole application to be declared invalid – as
would be the case if an individual made such a serious and misleading
mistake in a planning application.
SAFETY ZONE
- The evidence obtained from the Dr. Jerry Havens’
Report (see. attachment 1), prepared by the Public Utilities Commission of
the State of California for the Federal Energy Regulatory Commission,
highlights worrying scientific evidence. Dr. Havens, Distinguished
Professor of Chemical Engineering at the University of Arkansas and
Director of the University’s Chemical Hazard’s Research Center, concluded
that people living within 3 miles of the proposed
site would be in harm’s way (this radius covers the Kerry villages of
Tarbert and Ballylongford and the Clare village of Killimer). “Dr. Havens
is extremely qualified and has studied LNG safety issues for more than 30
years. His primary specialisation is in the analysis and quantification of
the consequences of releases of hazardous materials into the environment,
with emphasis on the consequences that can occur as a result of toxic
and/or flammable gas releases into the atmosphere”. ”He has provided
detailed analysis supporting his conclusion that there should be a minimum
of 3 miles between an LNG terminal and a densely populated area. Anything
closer than 3 miles could put the public in harm’s way.” This
is based on a spillage of 3,000,000 gallons of LNG, which he claims is
widely accepted as credible.
However,
he also examines the consequences of a vapour cloud fire which could result if
the LNG spill vapours were not immediately ignited and a vapour cloud formed.
The cloud thus formed would drift downwind until it reached an ignition source
or became diluted below the flammable concentration level - after which time it
would not constitute a hazard. In his opinion, the maximum distance downwind to
which portions of a cloud (sufficiently large to constitute a severe fire
hazard) formed from the rapid spillage onto water of 3,000,000 gallons of LNG
could be ignited is approximately 3 miles. If the vapour cloud were ignited as it
drifted downwind, those persons in that area or immediately adjacent (thermal
exposure could occur at some distance beyond the edge of the fire) who could
not gain protection could be killed or seriously injured.
In
any case, he states that such fires cannot be extinguished and would just have
to burn themselves out.
Havens
also deals with the explosion hazards of confined vapour cloud explosions,
unconfined vapour cloud explosions, boiling liquid expanding vapour explosions,
Toxicity hazards, Cryogenic (“cold” burn) hazards and Rapid phase transition
(flameless explosion) hazards. Their importance in the public safety context
lies in the potential for RPT’s to cause secondary damage which could lead to
cascading failures and further releases of LNG.
Dr.
Havens’ report is based on a spill of 3
million gallons. The EIS submitted by Shannon LNG proposes
(volume 1 page 3) to design a jetty capable of taking ships with a capacity of
up to 265,000 m3 of LNG. This is equivalent to 58 million gallons approximately.
The
distance of the proposed site from vulnerable residential areas must therefore
be taken into account by An Bord Pleanála.
- The limited QRA implemented by Shannon LNG goes
even further than the Havens’ report when it admits that a vapour cloud
could travel up to 12.4
kilometres before being ignited:
“A rule-set has been created for the QRA by
considering the development of the largest cloud produced by the consequence
analysis, that for catastrophic failure of a full tank in F2 weather. This
cloud has a maximum downwind distance to LFL [lower flammable limit] of 12.4
km.” (they do not state how far the cloud could travel beyond this distance
before it meets the upper flammable limit – the level at which the oxygen mix
with the gas is so high that the gas can no longer be ignited).
LNG FIRE HAZARDS
- A report by the IoMosaic Corporation –
“Understand LNG Fire Hazards” (see attachment 19 page 15) found that the maximum impact hazard
footprint of a 200,000 m3 LNG tanker will result from a pool fire leading
to a fatality limit of 50 percent at a distance of 3.7 kilometres from the leak.
- The safety zone of 3 miles conservatively required
by the Havens’ report has implications for further residential development
in the area surrounding the gas terminal. It will potentially have the
effect of sterilising residential areas (stopping any new houses from
being built on safety grounds) and
it will also prevent other areas of the landbank from being developed as
the levels of risk increase with more complex developments side by side.
Shannon LNG proposes in the EIS
(volume 1 page 5) that the remainder of the site may be used for a
gas-fired power station , but the exclusion zone of 3 miles will make this
proposal untenable. The Bord is asked to take these issues into
consideration and issue an opinion on them as they will have serious
social and economic long-term consequences on the area. In any case,
Article 12 of the EU Seveso II directive states: “Member States shall ensure
that their land-use and/or other relevant policies and the procedures for
implementing those policies take account of the need, in the long term, to
maintain appropriate distances between establishments covered by this
Directive and residential areas”.
- SIGTTO (The Society of
International Gas Tanker and Terminal Operators Ltd) is a non profit
making company, formed to promote high operating standards and best
practices in gas tankers and terminals throughout the world. It provides
technical advice and support to its members and represents their
collective interests in technical and operational matters. To become a full Member of SIGTTO it is necessary
for a company to have equity interest in or to operate a gas tanker or
terminal. Two of the company’s published works are
- “LNG Operations in Port Areas : Essential best
practices for the industry” (see.
attachment 2) which SIGTTO describe as follows: "This document draws on
this collective experience in setting out guidance to best practice for
managing gas shipping operations within ports. It also illuminates the profile
of risks attaching to gas operations, for the information of those who
administer", and
- “Site Selection & Design (IP no.14) for LNG
Ports & Jetties” (see. attachment 3) which SIGTTO describe as
follows: “Information Paper No.14: Bearing in mind the high consequential risks
of a serious accident in the LNG trade, this publication has been prepared for
port developers as a guide to the minimum design criteria considered necessary
when a port is to be built or altered to accommodate LNG carriers.” Although
HESS is not a member of SIGTTO, in the absence of direct Irish or EU regulation
on the matter, it is only reasonable to expect that HESS would follow the
standards set by its own industry.
In
the public meeting held at the “Lanterns Hotel” in Tarbert on October 29th 2007, Shannon LNG stated that the SIGTTO standards were “a wish list for the
ideal site, which was not, in any case, binding on Shannon LNG”. We object
extremely strongly to this claim because the Gas industry’s own standards
should be a minimum that the Kilcolgan Residents Association would expect to be
applied. The Bord is fully entitled to regard that response from Shannon LNG as
an admission that the present application does not match what they accept is “a
wish list for an ideal site”. There is no objective reason why the Bord should
depart from that standard when assessing this application. The Bord has the
opportunity, as well as the Statutory obligation to maintain the highest
possible standard and the Company’s statement eloquently describes exactly what
that standard is
RISK
ASSESSMENT
- a) SIGTTO clearly state in “LNG Operations in
Port Areas:Essential best practices for the industry” that risk exposures
entailed in an LNG port project should be analysed by a Quantitative Risk
Assessment (QRA) study which “must involve the operations at the terminal and
the transit of tankers through the port” (Section 2 page 5).
Shannon
LNG have only undertaken a QRA for the storage tanks on the shore, but no
QRA has been done on the marine side of the operation. This is not in line
with the industry’s own best practice guidelines. The QRA includes a tanker on
the jetty but it does not consider ship collision between two ocean-going
vessels. It should be bourn in mind that tug boats themselves can also be a
cause of collision
b)
The SIGTTO standards also clearly state (page 7) that any risk-mitigating
factors introduced - such as traffic control, exclusion zones around transiting
tankers, tug escorts and specified limiting operating conditions of wind speed
and visibility – should also be used in the QRA. This has not been done.
c)
No QRA of intrusive risk exposures has been undertaken either. There are two
categories of intrusive risk; that arising from intrusions threatening the
physical integrity of the terminal and berthed tankers (e.g. heavy displacement
ships), and that arising from the introduction of uncontrolled ignition
sources.
d)
Shannon LNG (in EIS Volume 2, section 3.10.2.3) states that “Shannon LNG
understands that a more detailed Quantitative Risk Assessment (QRA) covering
all navigational aspects of shipping will be undertaken by Shannon Foynes Port
Company during development of the project”. This splitting of risk assessment
responsibility is not acceptable and indeed dangerous. Furthermore this is
contrary to the EU 1998 Aarhus Convention Directives, Directive 2003/4/EC and
Directive 2003/35/EC which declare the right of the public to be informed on
environmental impact and to be provided with the opportunity to make comments
and have access to justice.
e)
The Quantitative Risk Assessment is based on “Land-use Planning Advice for Kilkenny
County Council in relation to Grassland Fertilisers (Kilkenny) Ltd at
Palmerstown”. This is completely inadequate for a risk assessment of an LNG
installation because the chemicals are different and the manner in which they
leak is completely unique to LNG because it is at such a low temperature (-160
degrees).
f)
One obvious and questionable claim in the QRA undertaken by the developer can
be seen where only one of the four LNG storage tanks is covered by the inner
zone contour in Figure 6.2 of the QRA on page 59. This means (using the
criteria of table 5.1 on page 49) that it would be acceptable to build
residential houses up against the remaining 3 LNG storage tanks even if the
first tank leaks. This does not make sense and can only lead to the conclusion
that the contours have been unrealistically tightened so as not to encompass
current residential areas. We therefore object to this QRA which has not been
made available to the general public.
h)
We request more time from An Bord Pleanála to get our own independent technical
assessment of the QRA undertaken by the developer because it has only been made
available to us a very short time ago and is still not available to the general
public.
i) Misapplication of Risk Assessment: Recently
it has become popular on the international front to apply risk assessment to
justify otherwise poor decisions not necessarily in the best interest of the
public or the country. RA can be a very unwise tool to force the will of
a powerful few on the uninformed public. One factor signalling some very
poor applications of RA is the comparison to other risks that in a technical
reality are not really related, especially as to consequences. Some
consequences are so great that no matter what the probability the risks cannot
be justified, especially if economic benefit to the decision makers is actually
driving the poor application of this tool. A reality test in such poor
applications is to ask what the real liability of the organisation is, if their
risk call (aka their key technical “facts” assumptions) should prove wrong.
Are their liabilities, both economic and criminal, for reckless decisions
shall we say, limited by layers of attorneys citing loopholes, are the real
assets moved off shore or to another country? What are the real corporate
risks here if the RA is incomplete, inaccurate, or poor?
SITE SELECTION
- SIGTTO clearly state criteria which must be
followed in “Site Selection and Design for LNG Ports and Jetties”. These
include (page 12):
- Find a location suitably
distant from centres of population
- Provide a safe position,
removed from other traffic and wave action. For an “LNG carrier of about
135,000 m3 capacity, the waves likely to have such effects are those
approaching from directly ahead or astern, having significant heights exceeding
1.5 metres and periods greater than 9 seconds” (page 7). The EIS submitted by
Shannon LNG proposes (volume 1 page 3) to design a jetty capable of taking
ships with a capacity of up to 265,000 m3 of LNG so the port criteria must
satisfy this capacity of ship
These
criteria seem to be unobtainable given the proximity of the villages of
Ballylongford, Tarbert and Killimer (all 3 miles from the proposed gas
terminal) and the huge amount of ships using the estuary already. Also, windage has to be accounted for because the specific gravity of LNG is a
lot lower than oil and so the ship runs a lot higher on the water.
MOVING SAFETY ZONE
- SIGTTO clearly state in “Site Selection and“LNG
Operations in Port Areas:Essential best practices for the industry”, that
it is sound practice to establish a cordon sanitaire or exclusion zone
around a transiting gas tanker. “Where traffic is proceeding in the same
direction as the tanker the zone may extend some 1 to 2 miles ahead of the
gas carrier, a distance determined by the distance required to bring the
following gas carrier safely to a stop. Traffic following the gas carrier
should be excluded for a similar distance, allowing scope for the gas
carrier to slow down to manoeuvre without it being impeded by the approach
of following ships. In general, traffic should not cross closer than 1.5
miles ahead or 0.5 miles astern of a gas carrier” (page 15).
a)
These conditions have therefore an effect on the traffic moving through the
estuary towards Tarbert, Moneypoint, Foynes, Aughinish and Limerick, especially
since Shannon LNG have plans for 125 ships a year coming to the gas terminal
b)
This also has an effect on the Tarbert-Killimer car ferry.
c)
This also has an effect on all leisure boats using the estuary, including
dolphin watchers in this SAC area of the Lower Shannon and the boats from
Saleen Pier.
d)
Furthermore, the exclusion zone will prevent other sea-based industries setting
up in the land bank as they will not be able to access the site when LNG
tankers are at port.
ENVIRONMENTAL POLLUTION: SEAWATER USE POLLUTING THE
SHANNON ESTUARY:
- Intermediate Fluid Vaporizer (IFV) technology
using the Shannon seawater as a heat source is the intended method by
which Shannon LNG will convert the liquid LNG to gas. The EIS (volume 2
page 63, section 3.6.3.2), notes that up to 5 pumps will be used to
circulate up to 20,000 cubic metres of water per hour. This equates to 4.4
million gallons per hour. To
prevent marine growth (bio-fouling) within the system, sodium hypochlorite
(bleach, an oxidiser) will be added to the seawater on a continual basis.
As it exchanges heat with the glycol solution, the seawater will be cooled
such that at discharge it is cooler than the ambient seawater.
The
withdrawal and discharge of huge volumes of seawater (over 100 million gallons on a
daily basis) would affect marine life by killing ichthyoplankton
unable to escape from the intake area (see attachment 4) . Further, the
discharge of cooled and chemically-treated seawater would also affect marine
life and water quality. For this reason, open-loop technology (and the Shannon
LNG proposal is still an open-loop seawater technology even if it is using a
closed-loop glyclol system) has been successfully opposed continuously by
government bodies due to its negative environmental impact. This is because IFV
technology poses the same environmental problems faced by Open Rack Vaporiser
(ORV) technology which also relies on huge quantities of seawater (see
attachment 7, section 3.5.2.3). It must be remembered that the Lower Shannon
waters (including the 25 acres offshore of the proposed LNG site) are in a
Special Area of Conservation (SAC) designated area (see attachment 6) –
therefore constituting waters that must be protected under the EU habitats
directive.
The
waters of the Shannon can be protected using an alternative heating solution
e.g. a closed-loop vaporiszer but this will prove more costly for
Shannon LNG.
Concern
also has to be expressed on the effect of the additional surface water runoff
from the site and water supply to and from the proposed new pond (EIS volume 1
page 21) as well as the chemically-modified cooler seawater discharged from the
vaporising process on the wetland habitats to the north-west of the site.
THE
EU HABITATS DIRECTIVE
- The Bord is
bound to uphold the previsions of Art. 6 of the Habitats Directive and of
the Irish implementing measures. It is plain that the provisions of Art
6(3) apply to this development. It is also plain that the development will
by definition have negative implications for the lower Shannon Estuary
candidate SAC. The Bord therefore has no basis for finding that the
development will in the words of the Directive, “ not adversely affect the
integrity of the site”.
The applicant itself does not
purport to claim that the development comes within the provisions of Art. 6 (4)
of the Directive and in our view they are quite correct not to attempt to make
any such claim.
It is therefore not open to
the Bord to grant permission.
We also rely on the protection
afforded under European and Domestic law to the Ballylongford Bay proposed
Natural Heritage Area and the Shannon-Fergus Special Protection Area in
submitting to the Bord that the impacts of the development also mandate the
Bord to issue a refusal.
- The ecological sensitivity of the area has been
recognised in the Kerry County Development Plan (see appendix 22) in
declaring both Ballylongford Bay and Tarbert Bay as areas of Ecological
Importance. For this reason we object to any environmental damage to this
area.
- The Environmental Protection Agency, in its 2006
report on water quality in Ireland (see attachment 23) emphasised the need
to have, under the Water Framework Directive (WFD)(2000/60/EC) all waters,
both surface and groundwater in good or higher status by 2015. We
therefore object that the use of the Shannon waters as proposed in this
planning application directly ignore or obligations under the Water
Framework Directive.
PROJECT
SLICING
- Shannon LNG is artificially cutting this LNG
project into pieces for the purpose of winning legal approval. Through
this process, known as “salami-slicing”, sections of this project will be
assessed and permitted. The idea is that the less
environmentally-questionable parts of the project are authorised and built
first, making continued development of the project a virtual
fait-accompli, even if the latter sections of the project seriously
violate environmental regulations. This is contrary to, among others,
article 2.1 of the EIA (Environmental Impact Assessment ) directive, which
requires that “projects” likely to have significant effect on the
environment – not parts of projects – are subject to the assessment.
Shannon
LNG has made only vague reference to the pipeline from the proposed
gasification terminal to Foynes even though this pipeline could also pose
serious environmental and safety risks depending on the pressure of the gas in
the pipeline.
It
has only made vague references to its plans for the rest of its site on
the land bank. They suggest maybe a gas-fired power station which would, they
say, “be the subject of a separate planning application and EIS” (EIS volume 1
page5).
Shannon
LNG also states (EIS volume 1 page5) that electricity to be supplied via 110kv
lines from the ESB network at Tarbert will also “be the subject of a separate
planning application”.
Shannon
LNG goes on to state (EIS volume 1 page5) that Kerry County Council will
upgrade the coast road from Tarbert which “will also be the subject of a
separate planning application”.
It
is to be feared that, due to the necessary exclusion zone required for LNG
tankers, the land bank will only be fit for other “dirty” projects, which, if
assessed along with the LNG gasification terminal, would almost certainly be
denied planning permission.
This
piecemeal approach to the planning process is extremely questionable as it does
not deal with the sustainable development of the area.
LIMITED
GAS SUPPLY
- The justification for the project being that the
supply of gas to Ireland is not assured must be questioned and it cannot
be assumed that the proposed gas terminal is of overriding national
interest. Reference has been made to the threat from the Russian pipeline.
It must be pointed out that
- A gas pipeline also
exists from Norway to the UK (see attachment 8). After the start up of the
Langeled pipeline from Norway’s Sleipner platform to the UK in the autumn of 2006, shockwaves were sent
through the market. “History was made
when over-the-counter prices fell to negative territory for the first time”.
- LNG terminals in the
rest of Europe provide an indirect source of gas through the European network.
- Gas has been discovered
off the coast of Ireland
- Shannon LNG is giving no
guarantees of supply whatsoever. It is assumed that the intention of the gas
industry is to make LNG a commodity product where more gasification terminals
increases liquidity in the market and the LNG tankers can change routes more
easily if the spot price of LNG changes. From the Poten & Partners report
(see attachment 8) Ofgem, the UK regulator, had to invoke use-it-or-lose-it
provisions to stop BP and Sonatrach from diverting cargoes elsewhere to take
advantage of price movements. Shannon LNG do not want the same types of
provisions as can clearly be seen from the pre-planning consultation documents
from An Bord Pleanála.
- Gas is still a fossil
fuel and when the whole supply chain of LNG is considered from the extraction,
liquefaction, transport and gasification stages it is thought that LNG is no
cleaner than coal. This contradicts our national commitments signed up to in
the Kyoto Protocol
LNG:
UK Gas Sellers Face Looming Supply Glut
- Poten and Partners have issued a report on their
website of a looming glut of LNG in the UK market which should guarantee
the supply of LNG to Ireland (see attachment 8). They state that a rapidly
expanding import infrastructure in the UK threatens to outstrip
requirement by a large margin. “In addition to Langeld, operation of the
BBL and Tampen pipelines from the Netherlands and Norway will add 100 Bcm/y of new import
capacity by 2010, equivalent to half the country’s demand.” The report
also claims that “LNG import capacity will grow ten-fold during the same
period”. “This is thanks to the new dockside regasification facility at
Teesside in northeast England and two grassroots terminals under
construction at Milford Haven in Wales, known as Dragon LNG and South
Hook”, they add.
- The Government White Paper, “Delivering a
Sustainable Energy Solution for Ireland”, the Energy Policy Framework from
2007 -2020 (see attachment 9 section 3.3.2), states that in implementing
strategic goal 2 (ensuring the security and reliability of gas supplies):
“The
UK is now the source of some 87% of our natural gas and the UK’s own demand for
imports is growing strongly. Norway will remain a significant supplier of gas
to UK in the medium term. Ireland’s location in Europe from the view-point of
gas supply sources is becoming less peripheral. In the last 12 months the UK
has achieved a significant increase in gas import capacity through accelerated
infrastructure developments with resultant benefits for Ireland. Both pipeline
and LNG capacity has increased significantly. These include the Langeled
pipeline from Norway, the new pipeline from the Netherlands and new LNG
terminals at Milford Haven. Further expansion of LNG capacity and gas
interconnection is underway in the UK and Europe which will benefit Ireland in
terms of security of wholesale gas supplies within this regional market… the
prognosis for gas supplies is relatively secure as a result”.
The White paper goes on to state:
“We
will put in place an all-island strategy by 2008 for gas storage and LNG
facilities in light of the outcome of the all-island study”. This would represent
an independent strategic view of LNG facilities, rather than depending on the
non-independent representation by Shannon LNG. “He who pays the piper, calls
the tune”.
Therefore,
while awaiting the government’s all-island strategy for LNG facilities and
while noting that “the prognosis for gas supplies is relatively secure”, we
strongly bring to An Bord Pleanála’s attention that there is no over-riding
urgent, strategic imperative or immediate need for an LNG terminal in Tarbert
and that therefore, the “National Interest” cannot be used as an excuse to
prime over and ignore the dangers being posed to the safety of the nearby
populations in Clare and Kerry and the
environmental damage that will be suffered on the SAC waters of the Lower
Shannon which must be protected under the EU Habitats Directive if the
development is given the go-ahead.
ALTERNATIVE
LOCATION FOR AN LNG TERMINAL
- The Second International Conference of Renewable
Energy in Maritime Island Climates held in University College Cork in April
2006 suggested that Cork, close to the Kinsale Gas Field, would be an ideal site for an LNG
terminal (see attachment 10):
“In
the longer term it is important to fully explore and maximize geographical
diversification in gas supply. One potentially promising option is through LNG
(liquid natural gas) trade. This would provide give possibility to transfer gas
from remote countries (Algeria, Nigeria, Malaysia, Trinidad and Tobago, United
Arab Emirates and Qatar), without using pipelines, which are not economically
viable. An LNG terminal in Ireland could be constructed near Kinsale Gas Field,
connected to the gas platform, thus the existing gas pipeline from the gas
field to Inch can be used. In this way, LNG could be used provide at least a
quarter of national gas demand or be sufficient entirely for the Cork area. LNG
can also be used as seasonable gas storage at the LNG plant (liquefaction and
storage during warm season and vaporisation and injection into local pipelines
during cold period). This service can increase the volume of storage in
Ireland, which is currently limited to what is contained within the pipelines
and remaining reserves at the Kinsale Gas Field.”
- The Second International Conference of Renewable
Energy in Maritime Island Climates held in University College Cork in
April 2006 also noted (see attachment 10) that:
“Germany has already started the construction
of a gas pipeline from St-Petersburg to Germany under the Baltic Sea, avoiding
borders. This is expected to provide more reliable supply from Russia to the
West by 2010”.
- In 2006, a natural gas storage licence was
granted to Marathon Oil Ireland Limited at parts of the Kinsale facilities
(including the Southwest Kinsale Resevoir and wells, offshore platforms,
pipelines, compression, processing plant and the shore terminal) used from
time to time to inject, store and withdraw natural gas (see attachment 21,
schedule 1 page 19) . This would seem to suggest that the Kinsale Resevoir
would be a more ideal site for strategic gas storage than Kilcolgan.
PUBLIC
ACCESS TO INFORMATION, PUBLIC
PARTICIPATION AND ENVIRONMENTAL IMPACT ASSESSMENT
- Shannon LNG submitted a risk assessment to the
Health and Safety Authority on the same day it submitted the planning
application to An Bord Pleanála. The HSA will make a recommendation to An
Bord Pleanála based on its own examination of the risk assessment.
However, the risk assessment has never been made
available to the general public and neither has it been submitted to An Bord Pleanála.
This means that the public will not have access to vital environmental
information (e.g. the environmental impact of an LNG leak) before the deadline
of November 16th and people who would make a submission based on the
risk assessment are now being illegally deprived of participation in the
planning process. This is contrary to Article 6 of the EU EIA directive.
This issue can be solved by an order that the HSA or
Shannon LNG produces both the Risk Assessment submitted and the HSA assessment to an Bord Pleanála and that this information be disclosed to
the general public. Further submissions will have to be allowed from the general public
– not only oral (for example in an oral hearing) but more importantly in
written submissions. This is to take into consideration people who
would be unable to speak at an oral hearing but who would have serious concerns
they could put in writing. These
written submissions will therefore have to be allowed from all members of the
public who have not made a submission before November 16th in order
to maintain transparency in the planning process.
We object that the
division of responsibility for the Environmental Impact Assessment across a
number of bodies including, but not limited to, An Bord Pleanála and the EPA is
not clearly defined because the general public does not have all the
environmental impacts before planning permission is applied for in order to
participate fully in the planning process.
We as members of
the public concerned have been given 7 weeks to prepare this submission to the
bord. In that time we have faced a literally impossible task. We have been
denied access to critical documentation including the materials submitted to
the HSA and the HSA’s own documents and reports on that material. Yet that
material and the HSA analysis of it will without doubt form the basis of the
HSA’s opinion and the Bord in turn will rely on that opinion in the context of
the Seveso II Directive. By the time we are eventually able to access the
material to examine it further the Bord may have already dealt with the
application on an erroneous assumption about the contaminants in the LNG. The
Bord will have closed the door to further submissions from us. That is a clear
example of one of the ways in which we are being shut out from meaningful
participation in the process in flagrant breach of our rights under Irish and
European Law. Our rights in this regard are guaranteed by the provision of the
European Convention on Human Rights as adopted and as further made binding on
An Bord Pleanála by the European Convention on Human Rights Act 2003 as well as
by the principles of natural justice and the obligation on the decision makers
including the Bord to apply fair procedures. There are several other aspects
which are in breach of our rights including:
a) The complete inequality of arms between us and the applicant. This is
accentuated by the ability of the applicant to engage in pre-application
consultations with the Bord so that it can be advised on how to present the
application. The Bord has concluded, with no public input, that the application
is one fit to be dealt with as Strategic Infrastructure and has literally
pre-judged that vital issue. That in turn puts the Bord in a position of
objective Bias when it comes to assessing our contention that the application
is no such thing and should not be considered as such.
b) The Applicants have been granted ample time to liaise privately with the
Bord, to compile their material, to liaise with other Statutory bodies and to
finalise this application. It has done so over a period in excess of 12 months.
By contrast the local residents and other members of the public have been given
no access to the statutory decision makers and instead are expected to convey
our concerns in one fell swoop within 42 days of being granted sight of some,
but not all, of the necessary documentation. This is fundamentally unjust.
QRA NOT DOWNLOADABLE
- In a public meeting
held by Shannon LNG on October 29th 2007, it was stated that
the QRA would be available to the general public over the Shannon lng
website. However, this has never been downloadable and has therefore never
been available to the general public. This was reported by Catriona
Griffin to An Bord Pleanála and was noted by the Bord.
BUILDINGS TO BE DEMOLISHED
- We object to old buildings being demolished as
they represent a history of all the people that lived there over the
centuries. The old stone buildings also represent our national heritage as
they are built in the style of the region. As these houses are also used by bats, we object that the
homes of the bats will be destroyed, contrary to the Wildlife Act
1976/2000 and the EU Habitats Directive.
RESIDENTIAL AMENITY
- We object to the detrimental affect of the
proposed development on the lives of the nearby residents and general
public.
i. The Environmental Impact
Statement anticipates (EIS volume 1 page 17) that construction work will take
up to 4 years
ii. The Environmental Impact
Statement anticipates (EIS volume 1 page 17) that construction activities will
require 24-hour working at the site.
iii. Added to this are the enormous changes to the visual landscape proposed (EIS volume 1
page 11).
iv. The noise and vibration
impacts from construction traffic and blasting (EIS volume 1 page 17 and 18)
are expected to be within the EPA limits. However, this does not take account
of the fact that this area currently has hardly any noise whatsoever as it is
on a lonely coastal country road and that the changed level of noise over many
years is unacceptable.
v. In addition,
Ballylongford village is not designed to take the huge increase in construction
traffic expected.
vi. Trucks will come from
Tarbert to the site but workers cannot be prevented from approaching the site
from Ballylongford and no upgrade of the road between Kilcolgan and
Ballylongford is proposed. This very winding road is therefore going to prove
to be a death trap for the many people that currently walk on this road as a
leisure activity.
vii. We are afraid that
children might cut themselves on the barbed wire fencing proposed around the
site.
viii. We object to the storage
tanks proposed at 50 metres height and want them put underground on visual
impact and safety grounds
ix. We object to the blight
on the landscape from the water.
x. Tourists visiting the
County of Kerry after crossing over the Shannon on the Ferry from Killimer to
Shannon will not want to pass a dangerous industrial zone as proposed and this
will have a hugely negative impact on the tourism sector in the north Kerry
coastal regions beyond Ballylongford (Asdee, Beale, Ballybunnion). Furthermore,
the site will not be in keeping with the county’s reputation as one of
outstanding beauty and will destroy our image.
xi. The environmental damage
to the water caused by 100 million gallons of cooled, chlorinated water being
daily discharged into the estuary will have a negative impact on the oyster
farming on Carrig Island at the other side of Ballylongford Bay as well as the
reputation of Ballylongford as it hosts the Ballylongford Oyster Festival every
year (see attachment 18).
xii. The residents in the
area surrounding this proposed development will have to live with the constant
fear that an accident may happen at any time and this will be a constant source
of worry and fear, no matter how long the terminal works without an accident.
This is unfair to burden an innocent population with this threat and residual
risk.
xiii. The EIS does not include
the 2.9 metre barbed wire fencing in the photo montages and this is giving a
misleading image of the full visual impact of the proposed development
xiv. The EIS does not include
the proposed gas power station in the photo montage and this is also giving an
extremely misleading image of the full visual impact of the proposed
development.
xv. We object that the photo
montages in the EIS do not represent the true size of the tanks and ask that
this be confirmed independently.
xvi. We object that the huge
construction traffic will effect the safety of the children on the school bus
routes
RIGHT OF WAY
- The EIS (volume 2 section 15.5.2) states that the
right-of-way on the farm track at the western boundary of the LNG terminal
site used by anglers to access the shore “will not be accessible to
anglers when the LNG terminal is operational”. We object to this.
- The EIS (volume 2 section 16.14) claims that there
are no registered rights of way or wayleaves on the site. We object to
this because the site has always been used to access the shore for
swimming, for angling etc by all the Kilcolgan residents, and to access
the site owned by Stevie Lynch and John O’Connor of Lislaughtin.
HESS LNG’s OTHER LNG TERMINAL REFUSED PERMISSION IN THE USA
- The Weaver’s Cove
site ( see http://www.weaverscove.com/aboutus.html )describes Hess LNG as follows:
“Weaver’s Cove Energy, LLC, is owned by Hess LNG,
LLC, which is a joint venture owned equally by Poten & Partners and Amerada
Hess Corporation. A team of professionals that are among the most experienced
and reputable executives in the global LNG and energy industry manages Weaver’s
Cove Energy. The project team members have decades of experience in the design,
development and operation of large energy projects around the world, as well as
right here in Massachusetts.”
One
newspaper article described it as follows:
“The
river that runs past a proposed liquefied natural gas terminal in Fall River
isn't safe for frequent traffic by massive LNG tankers, the Coast Guard ruled
Wednesday in what could be a fatal blow to the controversial project (see
attachment 11 )”
And
another paper said:
“BOSTON --A
proposed liquefied natural gas terminal in Fall River may have been dealt a
fatal blow.
Share on Facebook
· Save this article
·powered
by Del.icio.us
The
Coast Guard has ruled the river approaching the Weavers Cove Energy project is
unsafe for navigation by massive LNG tankers.
The
decision affirms concerns the Coast Guard expressed last year. The agency has
since done an extensive review of the project.
A
major problem is the relatively short distance between two bridges on the Taunton
River. The Coast Guard found the safety risks of the 700 foot long, 80 foot
wide tankers navigating the 1,100 foot gap were too great.
A
Coast Guard spokesman says the ruling "kills the project, as
proposed."
Weavers
Cove officials did not immediately return calls for comment on the ruling” (see
attachment 12 and 13).
The
real lesson to be learned from the debacle at Weaver’s Cove is that Hess LNG
were stopped from building an LNG terminal on safety grounds even though they
claimed that what they were proposing to do was safe. Our interpretation of
this is that, no matter what the obstacle, Hess LNG will claim that they can
make it work and ignore their own standards of Best Practice and put people’s
lives at risk in order to “clinch the deal”. This further proves that Hess LNG
is not capable of self-regulation and the independence of their own risk and
environmental assessments have now to be seriously questioned. Furthermore, the
increase in LNG traffic all over the world will only increase the risk of an
accident and this only accentuates the need for the implementation of the
strictest safety standards. We therefore implore An Bord Pleanála to refuse
planning on safety grounds.
ACCOUNTABILITY
- Shannon LNG is described as a wholly-owned subsidiary of Hess LNG
Limited in the Environmental Impact Statement submitted by Shannon LNG to
An Bord Pleanála (Volume 1 page 1). However, it has not been pointed out
to An Bord Pleanála that Hess LNG is an offshore company
incorporated in the Cayman Islands (see attachments 15 and 16). In the
event of an environmental disaster at the plant Shannon LNG would be
liable for the costs of any loss to property and human life. However,
Shannon LNG has no assets of note. This can lead to problems in litigation
where cases can go on for decades as attempts are made in the courts to
apportion blame and liability. Companies can deny liability by creating
shell companies in different jurisdictions, where ownership of the land is
shared among some companies and ownership of the operations is shared out
among other companies – all in different jurisdictions with different
litigation laws.
Hess Corporation itself has never proposed that it
could accept from the outset all responsibility for any environmental or human
losses at the site for which Shannon LNG itself (or any other related
companies) could be held liable as if it still owned the site and operations
and that this liability would not be given away or sold without the express
permission of the local planning authority in Ireland (Kerry County Council).
This would have had the added advantage of creating an incentive for Shannon
LNG to maintain the highest environmental and safety standards.
However, we object to the fact that an offshore
company controls the private company that is applying for planning permission
to construct this dangerous LNG terminal in Tarbert.
LNG CONTRIBUTING TO GLOBAL WARMING
- In its report on LNG (see attachment 17),
Greenpeace found that the use of natural gas that has been liquefied and
transferred across the Pacific reduces the difference between natural gas
power plant CO2 emissions and coal power plant emissions by nearly half.
However, it also found that the development of LNG terminals would open up
nearly limitless quantities of natural gas to the energy markets and that
this shift threatens to turn natural gas, previously viewed as a
“transitional” fuel, into a permanent source of global warming gases. This
surely goes against the spirit of the Kyoto Protocol and we therefore ask
An Bord Pleanála to note this and refuse planning permission for the
project. Furthermore, this trend
towards an increased dependence on LNG increases reliance on
environmentally destructive fossil fuels and significantly delays the
possibility of moving towards renewable energy sources by creating a
costly infrastructure for LNG.
Furthermore,
the idea of building a Gas Power station on the site (EIS volume 1, page 5)
will increase the dependency on LNG as a permanent fuel rather than a
transitional fuel and we object to this result.
DISAGREEMENT AMONG EXPERTS ON THE DANGERS OF LNG
- A report for the US
Congress was undertaken by the United States Government Accountability
Office (see attachment 14) with advice from 19 of the world’s
top international LNG experts. The startling findings from this
report was that even they seem unable to agree, hence the reports
conclusion that the US DOE should carry out further tests on spills of
LNG. We therefore also feel that due to the uncertainty in judging the
risk to people’s safety, An Bord Pleanála should apply prudence and rule
against this planning application.
- In The GAO Report
for Congress (see attachment 14) the section on Cascading Tank failure is
illuminating as it states that the worst case scenario is a small hole in
an LNG carrier’s containment; this
is because the LNG Pool Fire will last longer close to the ship; so giving
more time to heat the adjacent tank. A big hole allows the LNG to empty
quickly from the tank in question so limiting the time any fire has to
heat the adjacent tank. For this danger posed to the nearby residents we
ask once again that An Bord Pleanála should apply prudence and rule
against this planning application.
HOUSES NOT DISPLAYED ON SITE MAP
- On the site map made
available to the public, there are 6 houses missing – namely those of
Raymond O’Mahony, Adam Kearney, Geraldine Carmody, Mrs. Kathleen
Finnucane and two other houses
belonging to the Finnucane family. We object that this is distorting the
number of homes immediately adjacent to the site and question if this is
also distorting the QRA.
NO BENEFIT TO KERRY
- There is no plan to
send any of the gas imported to Kerry. The only monetary benefit to Kerry
shall be the rates that will be charged to the terminal and we object that
this should influence the submission from Kerry County Council.
COMMUNITY ENGAGEMENT IN PLANNING
- The final Report
from the APaNGO project entitled ‘community engagement in planning
exploring the way forward’ (see attachment 20) was launched at the international APaNGO closing conference
in Brussels at the end of October 2007. The APaNGO project is one of the
first studies of community engagement and involvement at the European
level, covering findings from the seven Member States in North West Europe
(Belgium, France, Germany, Luxembourg, the Netherlands, the Republic of
Ireland, and the UK). It noted that the “legitimacy of any planning
decision will vitally depend on the quality of democratic input to the
process; without that input, decision-making itself will be discredited.
For
this reason, and from the Aarhus Convention Directives on the right of the
public to be informed on the environmental impact and being provided with the
opportunity to make timely comments and have affordable access to justice, we
therefore object that we do not have the financial means to challenge the EIS
and QRA presented by the developer who has access to unlimited resources
through Hess Corporation. This EIS and QRA are not independent. We need funds
to challenge this with our own safety and environmental experts and therefore
request that An Bord Pleanála puts those funds at our disposal in order to
maintain transparency and equality in the planning process, given that this is
for a complex chemical installation in a SEVESO II site.
QUESTIONABLE REZONING BY KERRY COUNTY
COUNCIL
- We object that the development is proposed on a
green field site – even if it has recently been zoned industrial (EIS
volume 2, section 4.6.3). In march 2007, the LNG site was rezoned from “Rural
General” to Industrial (see attachment 29)
“The
stated purpose of the variation was as follows:
The
purpose of the variation is to facilitate consideration of suitable development
of these lands in accordance with the provisions of section 5.2.9 of the Kerry
County Development Plan 2003-2009 which states: ‘lands have been identified at
Ballylongford/Tarbert as suitable for development as a premier deep-water port
and for major industrial development and employment creation’. The adoption of
this variation gives effect to objective ECO 5-5 of the Kerry County
Development Plan 2003-2009 which states: ‘It is an objective of Kerry County
Council to identify lands in key strategic locations that are particularly
suitable for development that may be required by specific sectors. Land in such
locations will form part of a strategic reserve that will be protected from
inappropriate development that would prejudice its long-term development for
these uses.”
a) If the LNG terminal goes ahead then the landbank will
not be a deep-water port as all other ships will be forbidden and unable to use
the port.
b) The creation of 50 long-term jobs does not constitute
“major employment creation”.
c) The LNG terminal is in actual fact a hazardous
chemicals installation, defined as the most dangerous of sites in EU
legislation – a Seveso II site. This does not fall under the type of
installation to be considered for the rezoned site because if it was the
intention of Kerry County Development Plan to include hazardous sites within the
landbank then Kerry County Council would never have given planning permission
for the new houses currently being built (such as that of Jayne Kearney) less
than 900 metres from the LNG tanks. Any new houses built after the LNG terminal
is constructed would constitute “inappropriate development” which means that
hazardous sites were never to be considered as appropriate development within
the landbank.
d) This Seveso II site will sterilise the remainder of
the site which means that the aim in the Kerry County Development Plan of
“major industrial development and employment creation” cannot be fulfilled.
e) The County Manager stated that sufficient natural
amenity lands had been reserved to the west of the site which included a
walking route to Carrig Island. However, Carrig Island is at the other side of
Ballylongford Bay and takes several miles by car to reach by driving through
Ballylongford.
f) The County Manager went on to state that “the impact
of development on the residential amenity of houses in the vicinity of zoned
industrial land will be dealt with at the planning stage”. This clearly shows
that the site is not intended for a SEVESO II development.
g) More importantly Clare County Council objected to the
rezoning on the grounds that:
“the proposed rezoning is likely to have
a significant impact on the future development of the region, and will have a
direct impact on the planned objectives for the Mid West Regional guidelines
for the Shannon Estuary and in particular the Planning, Economic and Service
Infrastructural development objectives for zone 5 of the plan. Any industrial
development including the construction of a deepwater harbour will have a major
impact on both the visual and ecological amenities of the area, and potentially
on the Lower Shannon Estuarine Environment, including the foreshore of County
Clare. Clare County Council would like an appraisal of any SEA investigation
which may have been undertaken in respect of the proposed variation”. The Kerry
County Manager replied: “Any future application of these lands will be subject
to an Environmental Impact Assessment. This process will ensure that any
proposals will take into account impacts on the visual and ecological amenities
of the area. A copy of the SEA screening report for the proposed variation will
be forwarded to Clare County Council.”
This
is reprehensible. There is no evidence of an SEA having been undertaken as
required for a variation to a development plan under Statutory Instrument No
436 of 2004 Article 7 section 13K and article 12 schedule 2A of the same
Statutory Instrument (http://www.irishstatutebook.ie/2004/en/si/0436.html#article12 ). Without any information in the public domain regarding the scoping or the
actual execution of an SEA (see attachment 32), this rezoning is fundamentally
unsound and invalid. Clare County Council does not even know that this is a
SEVESO II development. This rezoning process is also being brought to the
attention of the relevant authorities as we object that the variation and
rezoning of this site has been undertaken in a highly questionable and indeed
invalid manner. We therefore object to the planning application because we
maintain that this land is not zoned industrial.
These
points mean that An Bord Pleanála should rule that the proposed development
does not conform to the Kerry County Development Plan for the site, nor to the
Planning and Development Act and should therefore be refused planning
permission.
OTHER ISSUES
- We object to any
possible movement by road of LNG, due to the dangers and want this to be
confirmed by An Bord Pleanála.
- We need An Bord Pleanála
to rule clearly on the use that may be made of the rest of the landbank if
planning permission is given to the developer. We object that the rest of
the landbank will be sterilised. It must be remembered that if the Bord
allows other installations be built on the site near the gas terminal then
they will have an influence on the risk of an accident at the regasification
terminal. A clear ruling on this matter must be made.
- We need An Bord Pleanála
to rule clearly on how close residential property may be constructed to
the site. We object that people will not be allowed to build on their own
property close to the site due to the dangers.
- We need An Bord Pleanála
to rule clearly on the exclusion zone it recommends for boat users on the
Shannon Estuary and object that use of the Shannon will be hindered by LNG
tankers.
- We object that most
of the statutory bodies informed of the planning application will not have
time to make detailed submissions to An Bord Pleanála due to the minimum
time scale of 6 weeks from the date of planning application. This is such
a serious installation that considered opinions cannot be given in this
short timescale.
- Under Seveso II
regulations, we insist that An Bord Pleanála, if it decides to accord
Planning permission to the developer, gives a detailed ruling on the type
of emergency plan to be put in place, both onsite and offsite, and insist
on the implementation of an early-warning system to all residents within
12.4 kilometers, including (but not limited to) a form of public siren and
information to be given to the same residents on how to react to this
siren.
- The Tarbert Development
Association and The Ballylongford Development Association do not speak for
the residents surrounding the Kilcolgan site and we object to any attempt
to claim anything to the contrary as this does not represent local
consultation as far as we are concerned.
- Morgan Heaphy,
Glencullare, asked Shannon LNG to elaborate on the exclusion zone in a
written comment on one of the information days (see EIS Volume 4 ,
Appendix 1F) and this has never been answered in any format (other than
the words “limited exclusion zone” (EIS volume 4 appendix 3c) ) and
therefore this does not represent consultation with the nearby residents. We object that the
developer has always maintained that the site is safe and has kept such a
low profile in discussing safety issues that the general public has been
completely unaware of the issues in the euphoria of having new industry
and jobs coming to the area. This is completely against the spirit of the
planning process and we object to this serious misrepresentation of the
installation to our detriment and the developer’s economic advantage.
- We object to the
application of the Strategic Infrastructure Act 2006 as it applies to this
application as we are extremely worried about the possibility of “agency
capture”. By this, we mean that we are extremely worried that An Bord Pleanála
may inadvertently become compromised by having too close an interaction
with the developer during the decision making process. We expect An Bord Pleanála
to maintain a professional distance from the developer and to inform us of
all negotiations it has with the developer and to give us a right of reply
to all correspondence between the developer and the Board. In the interest
of public safety in this Seveso II development we require that all new
information be disclosed to the public and that the public be allowed
sufficient time to analyse the data and make further submissions, both
written and oral.
- A report on the LNG
blast in Algeria (see attachement 24) mentions the contaminant gases that
Lng is made up of. Note that when HSE ,Sandia and other regulators do
tests with LNG, it is with 100% pure Methane. We object that the level of
contaminant gases to be shipped by Shannon LNG have not been disclosed and
request that An Bord Pleanála ask the developer to state the level of
contaminant gases they expect to have in the LNG shipments and whether
they will vary depending on the origin of the LNG in order that a QRA be
undertaken and analysed with this information in mind:
“A 1980 Coast Guard study
titled "LNG Research at China Lake," states that LNG imported into
this country is often far from pure, and it reveals that vapour clouds made
from "impure" LNG actually explode as readily as the highly volatile
LPG. When natural gas is super-cooled and turned into a liquid, as much as 14 %
of the total cargo shipped as LNG may actually be LPG or other hydrocarbon
fuels, according to the Coast Guard report. Natural gas contains these other
fuels when it is pumped from the ground.
LNG containing these so-called "higher hydrocarbons" is known as
"hot gas" and has a higher energy content than pure methane. The
Coast Guard report reveals that vapour clouds of LNG containing at least 13.6 %
of these other fuels can detonate just like pure propane gas. The agency
concluded in its report that this deserves "special consideration, as the
commercial LNG being imported into the US East Coast has about 14 % higher
hydrocarbons." “
- Is the limited
exclusion zone proposed by Shannon LNG around the LNG tankers taking into
account the risk of an ignition source as well as the risk of a collision?
- Lloyds Casualty Week
dated September 16 2005 (see attachment 25, page 11/12) noted an LNG fire
from a pipeline leak in Kalakama, Nigeria started a wild fire covering 27
square kilometres. We object that the developer has not included pipeline
incidents in the QRA because the pipeline EIS has not even been completed.
This shows the dangers in slicing a project into several separate projects
for planning purposes.
- What is the thermal
flux that An Bord Pleanála would determine as acceptable? Is it 1.5
kw/m2.?
- We object that the
State does not determine the most suitable site in Ireland for an LNG
terminal, rather than a biased private-sector company applying for
planning permission.
- We ask that An Bord Pleanála take account of
the Buncefield Reports (http://www.buncefieldinvestigation.gov.uk/index.htm ).
- From speaking to people in Milford Haven it was
noted:
a) Jobs increased initially but the unemployment rate
increased when the jobs finished as some of the workers had settled down in the
area
b) Rental costs were high during construction which made
life more expensive for locals
c) Skilled labour (such as welders) were attracted away
from local industry so some local business suffered as a result
d) There are other construction works on top of one of
the tanks equivalent in size to a five-storey building. Will that be the same
in Tarbert?
e) Dolphins used to be resident in the Haven but left and
never came back
- We object that this LNG terminal would increase
or dependency on the Opec nations – contradicting Energy independence
objectives (e.g. windfarms where we have best windspeeds in Europe )
- We object that the permanent jobs to be created
will not be for unskilled labour (see attachment 27), which means that it
is likely that many will not be filled by locals.
- We object that since the government is still
giving licences for exploration that must mean more gas exists in the
country
- We want all archaeological sites protected (including the one near the jetty)
- We object that the bird and sea life will be
seriously impacted by the lights and the sounds
- We object that the gas tanks will be visible from
county Clare as that county will be expected to get all the disadvantages
and none of the advantages (rates) from this development.
- We object that we do not know if Shannon LNG has
options to buy more land but need to know this as it would be an
indication of their real intentions.
- We object to the idea of dumping soil and stone
from the site near to Scattery Island.
- The Climate Protection bill on the 3rd October was in the senate and it refers to a 3 % decrease per annum.
Facilitating the importation and dependence on more fossil fuels like LNG
goes against the spirit of the Climate Protection bill.
- We object that an offshore location for a
terminal would be safer than the onshore one proposed.
- We object that the terminal could hit house
prices. An article in the Kerryman newspaper dated October 17th 2007, page 5 predicts a 29% drop (see attachment 28).
- No Material Safety Data Sheets ( MSDS) have been
supplied with the EIS and we object that these have not been provided. We
ask that An Bord Pleanála obliges the developer to provide these and allow
us sufficient time to analyse them.
- While all chemistry is dangerous, we agree that
it is also feasible it the hazards can be contained. However, we object to
the real problem here which is one of scale. 4 tanks of LNG represent 2400
tanks of gas.
- We object that the HAZOP study is not available
to enable us and the general public participate fully in the planning
process as required by the EU EIA Directive. We ask that An Bord Pleanála
obliges the developer to put it at our disposition.
“A HazOp study
identifies hazards and operability problems. The concept involves investigating
how the plant might deviate from the design intent. If, in the process of
identifying problems during a HazOp study, a solution becomes apparent, it is
recorded as part of the HazOp result; however, care must be taken to avoid
trying to find solutions which are not so apparent, because the prime objective
for the HazOp is problem identification. Although the HazOp study was developed
to supplement experience-based practices when a new design or technology is
involved, its use has expanded to almost all phases of a plant's life. HazOp is
based on the principle that several experts with different backgrounds can
interact and identify more problems when working together than when working
separately and combining their results. “
The risks we are
especially interested in examining in closer detail include (but not limited
to);
a) Static electricity and how to control it.
b) Catastrophic damage in the pressurisation process.
c) Catastrophic damage at the stage where odours are
added to the gas with mercaptons.
d) Catastrophic damage at the stage where the glycol
reheats the LNG
- We object that no trucks should be travelling to
or from the site for 5 minutes before and after a ferry boat lands because
it has been noticed that the existing road network in Tarbert cannot take
ferryboat traffic as it is at the moment.
- We object that the full height of the storage
tanks was lied about. The EIS (volume 1 page 4 ) clearly states: “The
tanks will be a low-profile design and will be approximately 96m in
diameter and approximately 50.5m high”. This is extremely misleading as
this EIS volume 1 – the non-technical summary – was widely distributed to
the general public. From the drawings submitted to An Bord Pleanála (see
attachment 31) it can be clearly seen that only the top of the concrete is
50.5 metres in height; the top of the tank elevation is 60.5 metres and
|